[TriLUG] Peak10 BBQ & Beer mixer

Alan Sterger asterger at earthlink.net
Thu Sep 15 13:32:54 EDT 2011


This I don't understand.  Any decent emergency configuration draws power 
from the on-line UPS at all times with the transfer switch downstream, 
switching either generator or utility into the UPS.  The UPS buffers 
"hash on changeover", making any transfer seamless to the end user or 
equipment.

Cheers,

-- Alan Sterger

On 9/15/2011 12:00 PM, trilug-request at trilug.org wrote:
> For the monthly diesel
> generator test, you were required to turn off your desktop
> machine incase it didn't survive the hash on changeover. You
> would be considered responsible if the machine was left on
> and didn't survive.
>
> Joe
>    



More information about the TriLUG mailing list